Kurri Kurri Team reaches major milestone

Our Kurri Kurri Team reached a significant milestone this week on the Kurri Kurri Storage Pipeline. The last string section was successfully lowered-in, and the team is now focusing on the final tie-ins. By the end of the week, all 24 kms of the 42-inch high-pressure storage pipeline will be backfilled and the team’s attention will shift to reinstatement and hydrotesting.

This achievement brings us one step closer to completing this critical infrastructure project. A huge thank you to our dedicated team for their hard work and commitment.