Eastern Goldfields Pipeline

Type of project: Gas Infrastructure

Client: APA Group
Location: Murrin Murrin, Western Australia, Australia
Completed in: 2015

The Eastern Goldfields Pipeline Project totalled 293km of gas pipeline across the Great Victorian Desert from Murrin Murrin to two offtakes, one at KP83 and the second at KP293 in a region 12-hour drive north-east of Perth.

Spiecapag’s scope of work included all construction elements of the gas pipeline from clear and grade to re-instatement. The works included operating multiple work fronts, each delivering 5km of productivity per day on average to achieve project schedule.

The project was delivered early at both off-take points, enabling early commissioning and gas up of the pipeline, with no time lost due to injuries (LTIFR = 0).

Proactive environmental practices on the project resulted in the team being awarded industry environment awards for excellent fauna management.